Owner In-House Counsel Concerns in Large Construction Contracts


                               SHANNON ONOOK
               Senior Legal Counsel, TransCanada Corporation, Canada


When  an owner contracts for a new large energy infrastructure project in Canada there are
many  issues they need to consider before, during and after the contract has been signed.
In-house counsel can play a vital role in helping project teams achieve the desired outcome
of an on time and on budget project, but only if they are diligent and involved long before
a contract is ever signed. This paper will outline some of the major concerns an owner
should turn their mind to in the contracting process. In Canada, there is a very well-
developed body  of law on the Invitation to Bid process and this will be discussed in
comparison  with a Request for Proposals process, with pros and cons for each. Risk
allocation between the parties and the maturity of the scope of work are also major
considerations in determining the correct contract pricing methodology and should also be
explored in depth with the project team. Other major issues will be discussed including
change  orders, recovery plans, liquidated damages, dispute resolution and good faith
dealings.
The  diligent Owner spends  a considerable amount of time, resources and money   in
developing the elements of a construction project. A large project utilizes internal and
external personnel from engineering to cost accounting to supply chain and legal. There
are also dedicated project staff from construction managers to project controls. The Owner
is arguably the party most vested in having a successful project built on time and on budget.
Every aspect of scope development and contract formation should be performed with an
eye on this goal.
When  hundreds of man hours are spent by project teams developing scope, tailoring pricing
mechanisms,  and negotiating legal terms and conditions, at what point do those express
provisions get moved aside in favor of implied obligations and duties of good faith?
A. Invitation to Bid vs. Request for Proposals
The  leading Canadian case in procurement  law is R(Ontario) v Ron  Engineering  &
Construction (Eastern) Ltd., [1981] 1 SCR  11]. In this case, the province of Ontario
requested bids for a construction project. The bids were to be submitted with a $150,000
deposit, which would be forfeit if no construction contract was entered into by a successful
bidder. Ron Engineering submitted their bid and deposit, but realized that they had made a
$750,058 mistake in their bid. They informed the Province of the error and maintained that
because the bid contained an error it could not be accepted and refused to sign the contract.
The Province retained the deposit and awarded to the next highest bidder. They went to
court on the deposit, and the Province was successful. The concepts of Contract A and
Contract B were born.
A unilateral contract, like an offer or Contract A, comes into existence the moment a
bid capable of being accepted is submitted. One of its terms is that the bidder agrees it will
enter into Contract B on the terms of Contract A if they win the bid. Once Contract
A is set and a bid sent in, Contract B is also set. There is not a lot of flexibility, if any,
and parties need to ensure they are satisfied with both the terms of Contract A and Contract