GAO-26-108654 1 (July 15, 2026)

handle is hein.gao/nclwste0001 and id is 1 raw text is: 















Why   This Matters


Key  Takeaways


The Moab  Mill Site in Utah processed uranium ore primarily for the U.S.
government's nuclear weapons  program during the Cold War era. During this
time, the site generated massive amounts of tailings, which are leftover waste
after uranium has been removed from rock. Tailings were stored in an unlined
pond, and as a result, the surrounding groundwater has become contaminated
with uranium and ammonia-threatening   the nearby Colorado River. The
Department  of Energy's (DOE) Office of Environmental Management (EM) is
responsible for cleaning up the contamination through the Moab Cleanup Project
and coordinates with DOE's Office of Legacy Management (LM) to plan the
future long-term federal management activities for the site.

Senate Report 118-188  includes a provision for GAO to examine EM's efforts as
the Moab  Cleanup Project nears completion. We are providing information on the
laws and regulations relevant to cleanup efforts; the remaining scope, schedule,
and cost of the cleanup; EM's engagement with stakeholders regarding the future
use of the site; and EM's coordination with LM regarding long-term federal
management   of the site.


   EM has removed  and disposed of over 16 million tons of tailings and other
    debris from the Moab Mill Site and is planning to complete its cleanup
    activities at the site by 2029.
  The  Moab  Cleanup Project has cost approximately $970 million through fiscal
   year 2025, and the total cleanup cost is expected to be approximately $1.16
   billion.
   DOE  expects to transfer ownership of most of the Moab Mill Site to Grand
    County, Utah when cleanup is complete but has not made a final decision.
    DOE  intends to retain ownership of a limited portion of the mill site and all of
    the disposal site.
   If ownership of the mill site is largely transferred to Grand County, DOE
    prefers that the community decide the site's future use, and community
    stakeholders have proposed a plan that would include various recreational
    uses.
   EM and  LM are coordinating on the future transfer of the sites for long-term
    federal management through formal agreements and an integrated project
    team. However, they have not yet developed a plan for the transition.


Page 1                                                                  GAO-26-108654 DOE MOAB MILL SITE CLEANUP


Page 1


GAO-26-108654 DOE MOAB MILL SITE CLEANUP