GAO-06-817R 1 (2006-07-17)

handle is hein.gao/gaocrptatqh0001 and id is 1 raw text is: 



  S=GAO

        Accountability * Integrity * Reliability
United States Government Accountability Office
Washington, DC 20548


          July 17, 2006

          The Honorable Sherwood Boehlert
          Chairman
          The Honorable Bart Gordon
          Ranking Minority Member
          Committee on Science
          House of Representatives

          Subject: NASA: Long-Term Commitment to and Investment in Space Exploration
          Program Requires More Knowledge

          The National Aeronautics and Space Administration (NASA) plans to spend nearly
          $230 billion over the next two decades implementing the Vision for Space
          Exploration. In January 2006, NASA publicly released its Exploration Systems
          Architecture Study (ESAS), which is an effort to identify the best architecture and
          strategy to implement the President's 2004 Vision for Space Exploration (Vision).'
          The cost estimate for implementing the ESAS through fiscal year 2011 exceeds $31
          billion. The estimate through fiscal year 2018 is over $122 billion, and the estimate
          through fiscal year 2025 is nearly $230 billion.2 These estimates include the
          architecture, robotic precursor missions, supporting technologies, and funding
          needed to service the International Space Station (ISS).3 NASA plans to implement
          this architecture through a go as you can afford to pay approach, wherein
          lower-priority efforts would be deferred, descoped, or discontinued to allow NASA to
          stay within its available budget profile. This approach assumes NASA's budget will
          increase moderately to keep pace with inflation. Given the long-term fiscal
          imbalances that will challenge the entire federal government now and in the future, it
          would be prudent for NASA to establish a program that reduces the risk that
          significant additional funding, beyond moderate increases for inflation, will be
          required to execute the program.4 Government leaders will have to make difficult


          'The ESAS architecture supports the development of a new Crew Exploration Vehicle (CEV), Crew
          Launch Vehicle (CLV), a Cargo Launch Vehicle (CaLV), and other supporting systems. The architecture
          also calls for various Research and Technology (R&T) and Robotic Lunar Exploration Program (RLEP)
          projects.
          2 All cost estimates related to the Vision are reported as inflated (real year) dollars.
          3 NASA's cost estimate through 2011-$31.2 billion-included the costs of the R&T and RLEP projects
          needed to support the architecture. Its estimate for the first lunar landing-$104 billion-did not
          include $18 billion in funding for R&T and RLEP projects. To ensure consistency, the estimates for
          2018 and 2025 are presented with R&T and RLEP funding included.
          4 GAO, 21st Century Challenges: Reexamining the Base of the Federal Government, GAO-05-325SP
          (Washington, D.C.: Feb. 2005); 21st Century: Addressing Long-Temn Fiscal Challenges Must Include
          a Reexamination of Mandatory Spending, GAO-06-456T (Washington, D.C.: Feb. 15, 2006); and


GAO-06-817R Exploration Cost and Schedule


Page I