GAO-06-222R 1 (2005-12-15)

handle is hein.gao/gaocrptashh0001 and id is 1 raw text is: 




    A, GA 0
         A ountabiity  Integrty - Relabidlty
United States Government Accountability Office
Washington, DC 20548





                                    December 15, 2005

                                    The Honorable John W. Warner
                                    Chairman
                                    The Honorable Carl Levin
                                    Ranking Minority Member
                                    Committee on Armed Services
                                    United States Senate

                                    Subject: Unmanned Aircraft Systems: Global Hawk Cost Increase
                                    Understated in Nunn-McCurdy Report

                                    To provide for oversight of cost growth in DOD major defense acquisition
                                    programs, Congress passed legislation, commonly referred to as Nunn-
                                    McCurdy, which requires DOD to notify Congress when a program's unit
                                    cost growth exceeds (or breaches) the latest approved acquisition
                                    program baseline by at least 15 percent.' If the cost growth has increased
                                    at least 25 percent over the baseline, the Secretary of Defense must certify
                                    to Congress that (1) the program is essential to national security; (2) no
                                    alternatives exist which will provide equal or greater military capability at
                                    less cost; (3) new program acquisition or procurement unit cost estimates
                                    are reasonable; and (4) the management structure is adequate to control
                                    unit cost.

                                    On April 13, 2005, the Acting Secretary of the Air Force formally notified
                                    Congress that the procurement unit cost of the Global Hawk had increased
                                    18 percent over the baseline estimate. As you requested, we are in the
                                    process of reviewing the acquisition strategies and requirements for







                                    110 U.S.C. 2433 establishes the requirement for unit cost reports. The requirement became
                                    permanent law in 1982 in Public Law 97-252, section 1107. Two measures are tracked:
                                    procurement unit cost (total funds programmed for procurement divided by the total
                                    number of fully configured items to be procured) and program acquisition unit cost (total
                                    cost of development, procurement, and system-specific military construction divided by
                                    the number of fully configured end items to be produced). To eliminate the effects of
                                    inflation, costs are expressed in constant base year dollars.


GAO-06-222R Global Hawk Unit Cost Increases


Page 1