          Decision


          Matter of: Department of the Army-Modification of Remedy

          File:       B-292768.5

          Date:       March 25, 2004

          Richard B. Oliver, Esq., and Gregory M. Murphy, Esq., McKenna Long & Aldridge, for
          the protester.
          Capt. Tami L. Dillahunt, Army Materiel Command, for the agency.
          Louis A. Chiarella, Esq., and Christine S. Melody, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          Protest costs, including attorneys' fees, need not be allocated between protest issue
          that was sustained and issues that were not addressed or denied in decision where
          all issues were related to the same core allegation, which was sustained; since issues
          not addressed or denied were not distinct and severable from the sustained issue,
          attorneys' fees relating to those issues are reimbursable.
          DECISION

          The Department of the Army requests that our Office modify our decision,
          Continental RPVs, B-292768.2, B-292768.3, Dec. 11, 2003, 2004 CPD   -, insofar as
          that decision recommended that the protester be reimbursed the costs of filing and
          pursing its protests, including reasonable attorneys' fees. The agency contends that
          it should not be required to pay attorneys' fees concerning protest issues on which
          the protester was unsuccessful.

          We affirm our decision.

          Continental protested the award of a contract to Griffon Aerospace, Inc. under
          request for proposals (RFP) No. DAAHO1-02-R-0158, issued by the Army Aviation and
          Missile Command (AMCOM), Department of the Army, for the acquisition of an
          aerial remotely piloted vehicle target (RPVT) system and services. Continental
          argued that AMCOM's evaluation of proposals, including the evaluation of Griffon's
          past performance, was unreasonable and that the resulting award decision was
          improper.