B-286155.2 1 (2001-10-10)

handle is hein.gao/gaocrptamlr0001 and id is 1 raw text is: 




         G     A     0                                                 Comptroller General
             SIntegrity Reliability                                     of the United States
 ~ccountabthty Inert Rea iy
United States General Accounting Office            DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                 The decision issued on the date below was subject to a
                                                     GAO Protective Order. This redacted version has been
                                                     approved for public release.

          Decision


          Matter of: 4-D Neuroimaging

          File:        B-286155.2; B-286155.3

          Date:        October 10, 2001


          Richard B. Oliver, Esq., and William V. Walsh, Esq., McKenna & Cuneo, for the
          protester.
          S. Gregg Kunzi, Esq., Howard M. Holstein, Esq., and Michael J. Vernick, Esq., Hogan
          & Hartson, for CTF Systems, Inc., an intervenor.
          Deirdre L. Stallworth, Esq., Frederick M. Quattrone, Esq., and Michael Trovarelli,
          Esq., Defense Logistics Agency, for the agency.
          Paul E. Jordan, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO,
          participated in the preparation of the decision.
          DIGEST

          1. Technical evaluation identifying various features of awardee's proposal as
          advantages was unobjectionable where agency followed solicitation's evaluation
          criteria and record establishes that evaluated advantages have a reasonable basis.

          2. Agency's waiver of testing requirement included in solicitation by mistake did not
          prejudice protester where cost of the testing is de minimis; reducing protester's price
          by cost of the testing would not have affected the price-technical tradeoff.

          3. Agency was not required to conduct discussions regarding what protester
          characterizes as perceived weaknesses in its proposal where proposal was rated
          acceptable under all factors and weaknesses were simply areas where awardee's
          higher-rated proposal had relative technical advantages.

          4. Price-technical tradeoff was reasonable where source selection official identified
          technical distinctions between competing proposals and specifically determined that
          higher technically rated proposal represented best value despite higher cost.
          DECISION

          4-D Neuroimaging protests the award of a contract to the Canadian Commercial
          Corporation (CCC), on behalf of CTF Systems, Inc., under request for proposals