About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline



B-258537.8 1 (1995-10-31)

handle is hein.gao/gaocrptabzb0001 and id is 1 raw text is: 


Comptroller General
of the United States
Washington, D.C. 20548

Decision


Matter of: ASI Personnel Services, Inc.--Reconsideration

File:       B-258537.8

Date:       October 31, 1995
Howard Stanislawski, Esq., and Gary Quigley, Esq., Sidley & Austin, for the
protester.
Mary G. Curcio, Esq., and John M. Melody, Esq., Office of the General Counsel,
GAO, participated in the preparation of the decision.
DIGEST

Request for reconsideration is denied where requesting party reiterates arguments
raised during the initial protest, raises arguments that could have been, but were
not, raised during the initial protest, and otherwise does not demonstrate that the
decision contains errors of fact or law.
DECISION

ASI Personnel Services, Inc. requests reconsideration of our decision, ASI Personnel
Servs., Inc., B-258537.7, June 14, 1995, 95-2 CPD   44. In that decision we denied in
part and dismissed in part ASI's protest against the award of a contract to Pentad
Corporation under request for proposals (RFP) No. DAAG60-94-R-0017, issued by
the United States Military Academy (USMA) at West Point for mess attendant
services.

We deny the request.

The solicitation provided for award to the offeror whose proposal represented the
best value to the government, based on an integrated assessment of the following
evaluation factors that were listed in descending order of importance: management
and staffing; quality control; and cost. After best and final offers were submitted
and evaluated by the source selection evaluation team (SSET), the source selection
authority (SSA) chose Pentad for award based on a proposal that was acceptable
under each evaluation factor and was priced $800,000 lower than the most highly
rated proposal. ASI protested that the agency misevaluated ASI's and Pentad's
proposals and was biased against ASI.


EVALUATION OF ASI'S PRICE PROPOSAL

In its request for reconsideration, ASI argues that our decision ignored ASI's
argument that the SSET improperly rated its price proposal as marginal. We did not


1091027