B-415907.3 1 (2019-01-22)

handle is hein.gao/gaobadvls0001 and id is 1 raw text is: 



GAOU.S. GOVERNMENT ACCOUNTABILITY OFFICE
441 G St. N.W.                                                  Comptroller General
Washington, DC 20548                                            of the United States
                                         .......................................................................................................................
                                            DOCUMENT FOR PUBLIC RELEASE
                                          The decision issued on the date below was subject to
Decision                                  a GAO Protective Order. This redacted version has
                                          been approved for public release.


Matter of:  AECOM-Inquip Joint Venture--Costs

File:        B-415907.3

Date:       January 22, 2019

Giovanni Ruscitti, Esq., Berg Hill Greenleaf & Ruscitti LLP, for the protester.
Alfred L. Faustino, Esq., Corps of Engineers, for the agency.
Noah B. Bleicher, Esq., and Peter H. Tran, Esq., Office of the General Counsel, GAO,
participated in the preparation of the decision.
DIGEST

This Office will not recommend reimbursement of protest costs where the agency's
cancellation of the solicitation, which rendered the protest academic, was not a
corrective action taken as a result of the protest.
DECISION

AECOM-Inquip Joint Venture (AIJV), of Greenwood Village, Colorado, requests that our
Office recommend that it be reimbursed the costs of filing and pursuing its protest of the
termination of its contract, which was awarded by the Department of the Army, U.S.
Army Corps of Engineers (Corps), under request for proposals (RFP) No. W91238-17-
R-0049, for the construction of levee improvements, including cutoff wall construction
and earthwork, to the Natomas East Main Drainage Canal levee at Reach H in
Sacramento, California. AIJV maintains that the Corps unduly delayed taking corrective
action in response to its clearly meritorious protest.

We deny the request.

BACKGROUND

On December 27, 2017, the Corps awarded the contract at issue to AIJV. Response to
Req. for Costs at 1. After receiving a debriefing, Nordic/Great Lakes E & I Joint Venture
(NGJV), the only other offeror in the competition, filed a protest on January 10, 2018