B-411073 1 (2015-04-30)

handle is hein.gao/gaobadrco0001 and id is 1 raw text is: 




        G     A    O                                                  Comptroller General
      Accountabilty * Integrity * Reliability                          of the United States
United States Government Accountability Office
Washington, DC 20548                                     DOCUMENT FOR PUBLIC RELEASE

                                                       The decision issued on the date below was subject to
                                                       a GAO Protective Order. This redacted version has
         Decision                                      been      for pi release.



         Matter of: ACC Construction-McKnight Joint Venture, LLC

         File:        B-411073

         Date:       April 30, 2015

         Karl Dix, Jr., Esq., Smith, Currie & Hancock LLP, for the protester.
         Joseph J. Dyer, Esq., Bennett D. Greenberg, Esq., and Rhett E. Petcher, Esq.,
         Seyfarth Shaw LLP, for Walsh Group Ventures, the intervenor.
         Travis D. Van Ort, Esq., Department of the Army, for the agency.
         Matthew T. Crosby, Esq., and Christina Sklarew, Esq., Office of the General
         Counsel, GAO, participated in the preparation of the decision.
         DIGEST

         Protest alleging agency unreasonably evaluated protester's construction schedule is
         denied where record reflects protester's schedule lacked adequate detail and
         evaluation was otherwise reasonable and consistent with terms of solicitation.
         DECISION

         ACC Construction-McKnight Joint Venture, LLC (ACC), of Augusta, Georgia,
         protests the award of a contract to Walsh Group Ventures, of Chicago, Illinois, by
         the Department of the Army, Corps of Engineers, under request for proposals (RFP)
         No. W912QR-14-R-0022 for construction of a high school at Fort Campbell,
         Kentucky. ACC alleges the agency's evaluation of its proposal was unreasonable.

         We deny the protest.

         BACKGROUND

         The solicitation, issued on June 20, 2014, contemplated the award of a fixed-price
         contract for the construction of a high school at Fort Campbell, Kentucky. RFP
         at 1, 4.1 The solicitation provided that award would be made on a best-value
         tradeoff basis considering the following factors, listed in descending order of

         1 Citations herein refer to pages of the .pdf documents in the agency report (AR).