           Decision


           Matter of:  B3 Solutions, LLC--Reconsideration

           File:       B-408683.5

           Date:       May 8, 2014

           Pamela J. Mazza, Esq., Alexander 0. Levine, Esq., Patrick T. Rothwell, Esq., and
           Peter B. Ford, Esq., PilieroMazza PLLC, for B3 Solutions, LLC, the requestor.
           Ronald K. Henry, Esq., Kaye Scholer LLP, for Government Logistics Support
           Services, LLC, an intervenor.
           Andrew Bramnick, Esq., Department of Defense, for the agency.
           Scott H. Riback, Esq., and Tania Calhoun, Esq., Office of the General Counsel,
           GAO, participated in the preparation of the decision.
           DIGEST

           Request for reconsideration of a prior decision sustaining a protest because the
           evaluation of awardee's proposal did not conform with the solicitation's terms is
           denied where the requester does not show that the prior decision contains errors of
           fact or law that warrant reversal or modification of our decision; the requester
           repeats arguments previously made, asserts new arguments that could have been
           raised previously, and disagrees with our decision.
           DECISION

           B3 Solutions, LLC, of Alexandria, Virginia, requests reconsideration of our decision
           in Gov't Logistics Support Servs., LLC, B-408683, et al., Dec. 3, 2013, 2014 CPD
           ]__, in which we sustained a protest challenging the award of a contract to B3 on
           the grounds that its proposal failed to conform to a material solicitation requirement.
           B3 maintains that our prior decision was erroneous.

           We deny the request for reconsideration.

           The request for proposals (RFP) at issue contemplated the award of a contract to
           provide logistics support services. These services primarily involved moving
           furniture and other office supplies for certain Department of Defense (DOD)
           agencies within the Pentagon and the National Capital Region, including the
           Property Management Branch (PMB) of DOD's Washington Headquarters Service