B-297807.2 1 (2007-10-18)

handle is hein.gao/gaobadaap0001 and id is 1 raw text is: 


  I

         G    A    0Comptroller General
WAS    Accountability * Integrity * Reliability                    of the United States
United States Government Accountability Office
Washington, DC 20548


             D  ..
         Decision


         Matter of:  Al Long Ford--Costs

         File:       B-297807.2

         Date:       October 18, 2007

         Ronald G. Acho, Esq., Cummings McClorey Davis & Acho, PLC, for the protester.
         Vera Meza, Esq., U.S. Army Materiel Command, for the agency.
         Jennifer D. Westfall-McGrail, Esq., and Christine S. Melody, Esq., Office of the
         General Counsel, GAO, participated in the preparation of the decision.
         DIGEST

         Protester's request for recommendation that it be reimbursed its proposal
         preparation and protest costs is denied where protester failed to submit an
         adequately documented claim in a timely manner and failed to make a reasonable
         attempt to reach an agreement with the agency prior to filing at Government
         Accountability Office.
         DECISION

         Al Long Ford (ALF) requests that we recommend that it recover $477,051.31 from the
         U.S. Army Tank-automotive and Armaments Command for the costs of preparing the
         proposal that it submitted in response to request for proposals (RFP) No. W56HZV-
         05-R-D 117 and for the costs of filing and pursuing its successful protest in Al Long
         Ford, B-297807, Apr. 12, 2006, 2006 CPD ¶ 68.

         We  deny the request.

         In Al Long Ford, we sustained ALF's protest against the rejection of its proposal and
         the award of a contract for light utility trucks to American Equipment Company. We
         found that the agency should not have found ALF's delivery schedule high risk and
         recalculated it to the protester's prejudice without raising the matter with the
         protester in discussions. Because the agency had proceeded with performance and
         the trucks were urgently required, we did not recommend that discussions be
         reopened; instead, we recommended that the protester be reimbursed its proposal
         preparation costs. We also recommended that the agency reimburse ALF for the
         costs of filing and pursuing its protest. Our decision advised that, in accordance
         with our Bid Protest Regulations, 4 C.F.R. § 21.8(f) (2007), ALF needed to submit its