About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline



B-294337 1 (2004-10-15)

handle is hein.gao/gaobacyvh0001 and id is 1 raw text is: 


  I

         G     A    0Comptroller General
 .. . .Accountability * Integrity * Reliability                      of the United States
United States Government Accountability Office        DOCUMENT   FOR PUBLIC RELEASE
Washington, DC 20548
                                                    The decision issued on the date below was subject to a
                                                    GAO Protective Order. This redacted version has been
                                                    approved for public release.

          Decision


          Matter of:  AIA-Todini-Lotos

          File:       B-294337

          Date:       October 15, 2004

          Michael A. Lewis, Esq., Braude & Margulies, for the protester.
          Damon  Martin, Esq., Department of the Navy, for the agency.
          Jonathan L. Kang, Esq., and Michael R. Golden, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          Protest challenging agency's evaluation of protester's joint venture proposal is
          denied where agency (1) reasonably identified risk based on the new joint venture
          partners' lack of experience working together; (2) reasonably identified risk
          consistent with the evaluation criteria concerning lack of coordinated oversight
          among the joint venture partners; and (3) reasonably disregarded two of protester's
          alternative construction schedules that did not follow the critical path method
          prescribed in the solicitation. Record does not indicate whether agency adequately
          considered protester's third early completion schedule; however, even maximum
          credit for that schedule would not sufficiently raise protester's score to establish
          prejudice.
          DECISION

          AIA-Todini-Lotos (ATL) protests the award of a contract under request for proposals
          (RFP) No. N33191-02-R-1078, issued by the Department of the Navy, Naval Facilities
          Engineering Command  to the Cooperative Muratori e Cementisi-C.M.C. di Ravenna
          (CMC) for construction of the MEGA 4 project at the Naval Support Activity,
          Sigonella, Italy. ATL challenges the Navy's evaluation of its proposal and the source
          selection decision.

          We deny the protest.

          BACKGROUND

          The RFP was issued on May 6, 2004 and contemplated the award of a fixed-price
          contract for construction of a new elementary and high school facility, temporary