DOCUMENT RESUME


02867  - (A2093203] (Restricted)

IAdministration  and Enforcement of Davis-Bacon Act]. 20144. Jujy
14,  1977. 8 pp.

Report  to Commanding Officer, Western Div., Departaent of the
Navy:  Naval Facilities Engineering Command, Western Div., San
Bruno,  CA; by  illiam N. Conrardy, Regional Manager, Field
Operations  Div.: Regional Office (San Francisco).

Issue  Area: Consum3r and Worker Protection: Standards, Laws, and
     Regulations Enforcement (903).
 Contact: Field Operations Div.: Regional Office (San Francisco).
 Fudget Function: Education, Manpower, and Social Services: Other
    Labor  Services (505).
Orqanization Concerned:  Department of Labor; Trepte Construction
    Co., Inc.
Authority: Davis-Bacon  Act. 29 C.F.R., subtitle A. AS.P.R.  ch.
     18.

         Among projects reviewed  for compliance with minium
vage determinations  of the Davis-Bacon Act in the Department of
Labor's Region IX was the corstruction  of bachelor enlisted
quarters at the Naval  Air Station, diramar, California, at a
cost of $2,421,392.  Various deficiencies were found.
Findings/Conclusions: The  Resident Officer in Charge of
Construction, San Diego Area,  who administers such contracts,
did not demand timely receipt of  certified payrolls nor reviev
them to assure that workers were  properly compensated for hours
worked, classified correctly for  job performed, and that only
authorized deductions were made. An inadequatei number of
employee interviews were performed. Daily reports  of
construction actions to the inspector were generally inaccurate.
Apprentice  :ertification and ratios were also deficient. Neither
the construction representative nor the procurement clerk
charged with enforcement iad formal training in labor  standards.
More labor standard specialists are needed.  Recommendations:  A
full labor standards compliance review should be performed for
the Miramar project. The results of the review as well as steps
planned to acquire and train the necessary resources to insure
adequate enforcement of the Davis-Bacon Act should he furnished
to GAO. (DJM)