Enhance Gieothermal Systems (EGS) Commercialization
July 28, 2026


Enhanced geothermal systems (EGS) use directional drilling and
hydraulic stimulation technologies to add porosity and fluid
circulation to locations of naturally occurring underground heat
to create conditions necessary for geothermal energy
production. Related closed-loop systems use some of the same
technologies and, along with EGS, can be collectively referred
to as next-generation geothermal. Of available geothermal
technologies, EGS have the greatest potential for utility-scale
electricity generation due to recent technological advances and
investments that have reduced related costs and risks. The future
viability of commercial-scale EGS remains uncertain, though,
with only one operational EGS plant in the United States as of
July 2026. This In Focus summarizes the commercial status of
EGS  and discusses selected issues for Congress, including
federal support for research, development, and deployment
(RD&D)   as well as remaining challenges, including operational
safety concerns and reported administrative hurdles.

Background on EGS Development

The development of EGS started in the mid-2000s, spurred
largely by a seminal Massachusetts Institute of Technology
(MIT) report, The1 Fnuure fJ Geohema Ene rgy (2006), and the
directional drilling and stimulation tools developed by the oil
and gas industry. Since then, the geothermal industry has been
developing and adapting tools and techniques to work within
high-temperature, high-pressure, chemically active geothermal
environments and to commercialize EGS.
In 2014, the U.S. Department of Energy (DOE) released the first
funding opportunity announcement (FOA) for an EGS
demonstration and commercialization program-which would
eventually become the Utah Frontier Observatory for Research
in Geothermal Energy (FORGE). In 2023, both Utah FORGE
and the private company Feno Energy (Fervo) announced
successful fluid circulations at their respective EGS test sites. In
November  2023, Fervo started producing electricity at its first
commercial EGS  plant (Project Red, in Nevada), supplying 3.5
megawatts (MW)  of electricity for Google data centers. Fervo
began drilling for a second, larger EGS power plant called Cape
Station in late 2023. The Cape Station phased development plan
targets the eventual production of 500 MW of electricity by
2028, with permitting approval for up to 2 gigawatts (GW) if
geological and market conditions warrant such expansion.

Commercial Interest and Developments

Federal Leasing and Record Geothermal  Lease Sales
Federal leasing involves many steps and review processes. After
a land management agency, such as the Bureau of Land
Management  (BLM),  reviews lands for suitability for leasing,
and solicits bids and selects the winning bid, the geothermal
developer completes exploration, drilling, construction, and
production steps. Each step is typically preceded by


environmental reviews and other federal oversight during
implementation-with  a full development timeline from lease to
operation of, typically, 7-10 years. For more information on
leasing, see CRS Report R48064, Consideai   /   Federal
Ieasig  ofOnshore Energy: Oil and Gas and Geothermal
Pow er.
In 2025 and 2026, geothermal developers invested record
amounts in federal lease sales demonstrating increasing
commercial interest. In October 2025, BLM held a geothermal
lease sale in Nevada. That sale generated $9.5 million in
revenue-the  largest geothermal lease sale in U.S. history. All
geothermal lease sales by BLM in 2025 generated $24.0 million
from 451,893 acres. In June 2026, BLM held a lease sale of
152,381 acres in New Mexico that generated $16.6 million in
revenue, a new single geothermal lease sale record.
Fervo's Record-Breaking Initial Public Offering
On May  13, 2026, Fervo held an initial public offering (IPO) of
stock. After targeting a company valuation of between $2 billion
and $3 billion in the months prior, Fervo launched the IPO with
a valuation of approximately $7.7 billion, and investor interest
increased share prices until valuation reached $10,21 billion by
the end of the IPO day. This was reportedly the largest
renewable energy IPO ever. Some public reporting on the
offering has concluded that this valuation indicated strong
interest in the company and in geothermal energy, and
confidence that geothermal energy could supply the baseload
power needed by increasing data center demand.
Expansion  of Geothermal Power  Purchase Agreements
Power purchase agreements (PPAs) are contracts between an
electricity consumer and a specific power plant or supplier to
deliver electricity-at an agreed-upon price and/or an agreed-
upon amount of electricity, over a contracted time frame.
In June 2025, DOE released its 2025 U.S. Geothennal Market
Report, which noted that from 2021 (the date of its previous
market report) to June 2025, 27 new geothermal PPAs had been
signed-an  increase over the nine geothermal PPAs signed
between 2015 and 2019. Of the 27 new PPAs, 12 were for next-
generation geothermal (either EGS or closed-loop).
Since June 2025, additional EGS PPAs have been announced.
Google signed an agreement for 115 MW from Fervo's new
Corsac Station to supply data center and cloud computing
demand. Multiple buyers, including Southern California Edison
and Shell Energy, signed agreements for the remaining capacity
of Fervo's Cape Station (500 MW total anticipated capacity).
In March 2026, Fervo and Google signed a 3 GW framework
agreement to provide Google's data centers with power through
2033. Google will have the right of first refusal to purchase up
to 3 GW of electricity from certain new Fervo projects, which
could result in additional PPAs_