Defense Primer: LGM-35A Sentinel Intercontinental

Ballistic Missile


The LGM-35A   Sentinel is an intercontinental ballistic
missile (ICBM) system that is expected to replace the
Minuteman  III (MMIII) ICBM in the U.S. nuclear force
structure. MMIII has served as the ground-based leg of the
U.S. nuclear triad-land-based ICBMs, submarine-
launched ballistic missiles, and nuclear-capable bombers-
since 1970. The Department of Defense (DOD), which is
using a secondary Department of War designation, under
Executive Order 14347 dated September 5, 2025, requested
$4.1 billion for Sentinel research, development, test, and
evaluation (RDT&E) in FY2026. This request assumed
$1.5 billion from FY2025 reconciliation legislation (P.L.
119-21), commonly referred to as the One Big Beautiful
Bill Act. The FY2025 reconciliation legislation included
$2.5 billion for Sentinel risk reduction activities. The
FY2026  budget request for the Department of Energy's
National Nuclear Security Administration (NNSA) included
$649 million for the W87-1 nuclear warhead for the
Sentinel. The FY2026 National Defense Authorization Act
(NDAA   P.L. 119-60) authorized $3.8 billion for Sentinel
RDT&E   and $649 million for the W87-1 warhead.
  WhatIs   an  ICBM?
A U.S. ICBM  can reach targets around the globe in
approximately 30 minutes after launch. During the first
three minutes, three solid fuel rocket motors power the
missile's flight. After the powered portion of flight, the
missile follows a parabolic trajectory toward its target. The
missile releases its warhead during the mid-course portion
of its flight, and the warhead continues to the target. Once
the President authorizes the launch of any U.S. ICBM, the
missile cannot be recalled or destroyed in flight. The same
is true for nuclear missiles launched from U.S. submarines.
In contrast, U.S. bombers can return to their bases, without
releasing their weapons, although their weapons also cannot
be recalled after their release.
The United States began deploying nuclear-armed ICBMs
in 1959, and has maintained these systems on alert, or
able to launch promptly, since that time. The Air Force
deployed the Atlas between 1959 and 1965, the Minuteman
beginning in the 1960s, and the Peacekeeper (or MX)
between 1987 and 2005. The Air Force bases its ICBMs in
hardened concrete silos, or launch facilities, located in
North Dakota, Montana, Wyoming, Colorado, and
Nebraska. The United States has periodically considered
alternative ICBM basing concepts to ensure survivability.
The   T,ranstion from      MInuteman
The MMIII, which is currently deployed in a single-
warhead configuration, but could carry up to three
warheads, entered the force in 1970. The Air Force has
replaced and updated many of the component systems on
the missile-a process known as life-extension-several


times over the past 50 years. The Air Force has stated that
some of these components may face reliability concerns as
they reach the end of their intended lifespans. After
conducting an Analysis of Alternatives in 2014, the Air
Force decided to replace MMIII with a new missile system
(originally Ground Based Strategic Deterrent) that would
serve through 2075. The Air Force argued that, when
compared with a life-extended MMIII, the new ICBM
would meet current and expected threats, maintain the
industrial base, produce a modular weapon system, and
reduce life cycle cost. The Air Force and Northrop
Grumman,  the Sentinel's lead defense contractor, planned
for the Sentinel to begin replacing MMIII in 2029.
Program Status
The Air Force plans to procure 634 Sentinel missiles, plus
an additional 25 missiles to support development and
testing, to enable the deployment of 400 missiles. The Air
Force also originally planned to modernize 450 silos and
over 600 facilities (see Figure 1).

Figure I. Sentinel Deployment  and Support  Locations


   EOiState Boundary                       200 MILES
   Launch Facility (LF) t Missile Alert Facility
Source: Air Force Global Strike Command, 2023.
In January 2024, the Air Force informed Congress that the
Sentinel program exceeded its initial cost projections,
positing at least a 37% increase (from $118 million initial