Congressional Research Service
Informning the legislative debate since 1914


                                                                                         Updated June 22, 2023

The Army's M -10 Booker (formerly known as Mobile Protected

Firepower (MPF)) System


What Is the Mobile Protected Firepower
(MPF) System?
The Army's MPF  system is intended to address an
operational shortfall in infantry units:

    Currently the Army's  Infantry Brigade Combat
    Teams  (IBCT)  do  not have a  combat  vehicle
    assigned that is capable of providing mobile,
    protected, direct, offensive fire capability.... The
    MPF  solution is an integration of existing mature
    technologies  and   components   that  avoids
    development which  would lengthen the program
    schedule.
Operationally, the Army wants the MPF to be able to:
    Neutralize enemy prepared positions and bunkers
    and  defeat heavy machine  guns  and  armored
    vehicle threats during offensive operations or when
    conducting defensive operations against attacking
    enemies.
In terms of the Army's overall procurement plans for MPF:

    The Army  Acquisition Objective (AAO) for MPF
    is 504 vehicles, with 14 MPFs  per IBCT.  The
    targeted fielding for the First Unit Equipped (FUE)
    is Fiscal Year (FY) 2025.

M  PF  Redesignated as the M-10 Booker
On June 14, 2023, the Army announced the redesignation
of the MPF as the M-10 Booker infantry assault vehicle.
According to the Army:

    The vehicle platform honors two enlisted Army
    soldiers who served our nation selflessly during
    times of great conflict - Medal of Honor recipient
    Private. Robert D. Booker, who perished in World
    War  II, and Distinguished Service Cross recipient
    Staff Sergeant Stevon A. Booker, who died from
    injuries sustained in Operation Iraqi Freedom.
The Army  noted the historical significance of the M-10
Booker:

    The Army's  last named combat vehicle platform
    was the M-1126  Stryker Infantry Carrier Vehicle,
    also named for two soldiers. Other combat vehicles
    named in honor of soldiers include the M-1 Abrams
    Main  Battle Tank,  the M-2  Bradley  Infantry
    Fighting Vehicle, and the former M-60  Patton
    Tank. The M-10 Booker is the Army's first vehicle
    to be named after a soldier who fought in a post 9/11
    war.


  Note: CRS Reports and Future References for MPF.
  Until the Army adopts the M-10 designation in official
  documents and replaces reference to MPF, CRS will continue
  to use MPF in reports for historical purposes and to avoid
  confusion.

MPF Acquisition Strategy
In November 2017, the Army issued a Request for Proposal
(RFP) for the Engineering and Manufacturing Development
(EMD)  phase and, in order to maximize competition,
planned to award up to two Middle Tier Acquisition (MTA)
contracts for the EMD phase in early FY2019.

  Middle Tier Acquisition (MTA) according to the Defense
  Acquisition University is a rapid acquisition approach that
  focuses on delivering capability in a period of 2 to 5 years. The
  authority to use MTA was granted by Congress in Section 804
  of the FY2016 National Defense Authorization Act (NDAA)
  (P.L. 114-92). Programs using MTA are not subject to the joint
  Capabilities Integration Development System (CIDS) and
  provisions of DOD Directive 5000.01 Defense Acquisition
  System. MTA consists of utilizing two acquisition pathways:
  (1) Rapid Prototyping, which is to streamline the testing and
  development of prototypes, and (2) Rapid Fielding, which is to
  upgrade existing systems with already proven technologies.

On December  17, 2018, the Army awarded two Section 804
Middle Tier Acquisition (MTA) Rapid Prototyping
contracts for MPF. The two companies awarded contracts
were General Dynamic Land Systems (GDLS), Inc.
(Sterling Heights, MI) and BAE Systems Land and
Armaments, LP  (Sterling Heights, MI). Each MTA Rapid
Prototyping contract was not to exceed $376 million. The
MTA   Rapid Prototyping contracts required delivery of 12
pre-production vehicles (from each vendor) for
developmental and operational testing, and a Soldier
Vehicle Assessment (SVA).
M  PF  Programn Status
The SVA  reportedly began in January 2021 at Fort Bragg,
NC-without   the BAE prototypes because of production
challenges-with testing running through June 2021. While
BAE  was unable to provide prototypes at the beginning of
testing, prototypes were eventually provided to the Army
for testing. During the assessment, soldiers evaluated
GDLS  and BAE  MPF  prototypes in a variety of operational
scenarios.
MPF   Low-Rate  Initial Production (LRIP)
Contracted  Awarded
On June 28, 2022, the Army announced the award of a
$1.14 billion contract to GDLS for the production and
fielding of up to 96 MPF systems (Figure 1). Delivery of