S. Rept. 119-103 1 (2026-02-11)

handle is hein.congrecreports/crptxaict0001 and id is 1 raw text is: AUTHENTICATED
U.S. GOVERNMENT
INFORMATION 4











                                                       Calendar No. 332
                  119TH CONGRESS               N   E                REPORT
                     2d Session J            SENATE                 119-103





                       BULL   MOUNTAINS MINING PLAN MODIFICATION


                                 FEBRUARY 11, 2026.-Ordered to be printed


                    Mr. LEE, from the Committee on Energy and Natural Resources,
                                      submitted the following

                                         REPORT

                                         [To accompany S. 362]
                    The Committee  on Energy and Natural Resources, to which was
                  referred the bill (S. 362) to allow certain Federal minerals to be
                  mined  consistent with the Bull Mountains Mining Plan Modifica-
                  tion, and for other purposes, having considered the same, reports
                  favorably thereon with an amendment  and recommends   that the
                  bill, as amended, do pass.
                                           AMENDMENT
                    1. On page 2, line 8, insert until the date that is 1 year from
                  the date of enactment of this Act before the period at the end.
                                             PURPOSE
                    The purpose of S. 362 is to allow certain Federal minerals to be
                  mined  consistent with the Bull Mountains Mining Plan Modifica-
                  tion.
                                      BACKGROUND  AND  NEED
                    Signal Peak Energy  is currently operating the Bull Mountains
                  Mine  No. 1, an underground coal mine near Roundtop, Montana.
                  The Mine is comprised of a checkerboard of State, Federal, and pri-
                  vate coal. The Department of the Interior first approved the Bull
                  Mountains  Mining Plan, which initially authorized mining of 140
                  acres of leased federal coal lands, in August 2013. In November
                  2013, Signal Peak proposed a modification to its mining plan that
                  would permit it to mine the remaining federal coal on its lease. The
                  Department  of the Interior first approved the modification ten
                  years ago, in 2015. The approval was challenged in the federal dis-
                     69-010