H. Rept. 119-174 1 (2025-06-30)

handle is hein.congrecreports/crptxahlm0001 and id is 1 raw text is: AUT-ENTICATED
US. GOVERNMENT
INFORMATION
      GP










                   119TH CONGRESS                                      REPORT
                      1st Session   HOUSE   OF REPRESENTATIVES         119-174





                      TO   AMEND PUBLIC LAW 99-338 WITH RESPECT TO
                                    KAWEAH PROJECT PERMITS


                    JUNE 30, 2025.-Committed to the Committee of the Whole House on the State of
                                     the Union and ordered to be printed



                      Mr. WESTERMAN,   from the Committee  on Natural Resources,
                                        submitted the following


                                           REPORT

                                         [To accompany H.R. 1044]
                     The Committee  on Natural  Resources, to whom was  referred the
                   bill (H.R. 1044) to amend   Public Law   99-338  with respect to
                   Kaweah   Project permits, having considered the same, reports fa-
                   vorably thereon without amendment   and recommends  that the bill
                   do pass.
                                     PURPOSE  OF THE LEGISLATION
                     The  purpose of H.R. 1044 is to amend Public Law  99-338  with
                   respect to Kaweah Project permits.
                               BACKGROUND   AND  NEED  FOR LEGISLATION
                     Southern  California Edison, a subsidiary of Edison International,
                   is one of the largest electric utilities in the United States, serving
                   roughly 15 million people over a 50,000-square-mile area in Cen-
                   tral, Coastal, and Southern California.' Since 1899, Southern Cali-
                   fornia Edison  has  operated  the Kaweah   Hydroelectric Project
                   (Project) on the Kaweah  and  East  Fore Kaweah   Rivers, located
                   near  the community   of Three  Rivers  in Tulare  County.2 The
                   Kaweah   Project has a generating capacity of 8.85 megawatts and
                   is split into three developments.3
                     In 1943, Congress expanded  the boundaries of Sequoia National
                   Park  and, in so doing, acquired lands that contained part of the

                     'Edison International, Our Companies, https://www.edison.com/.
                     2Southern California Edison Company, Kaweah FERC Project No. 298. January 2019,
                   https://www.sce.com/sites/default/files/inline-files/CUL1_BuiltEnvironmentTSR.pdf.